Endpoint Security Consolidation

PERT

Review the dependency network. Drag to pan, or use the scrollbars, to explore the full dependency map.

Critical pathCompleteDependencies
ES-P1-M01Planned

Name the sponsor, program owner, and consolidation decision rights

Govern and design the target endpoint program

2 person-daysCritical
ES-P1-M02Planned

Define the endpoint populations and operating systems in scope

Govern and design the target endpoint program

4 person-daysCritical
ES-P1-M03Planned

Establish a baseline endpoint and ownership inventory process

Govern and design the target endpoint program

4 person-daysCritical
ES-P1-M04Planned

Map the current endpoint tools, agents, owners, contracts, and data flows

Govern and design the target endpoint program

5 person-daysCritical
ES-P1-M05Planned

Define the required management, protection, detection, response, and reporting capabilities

Govern and design the target endpoint program

4 person-daysCritical
ES-P1-M06Planned

Record platform, remote-work, offline-device, and regulated-system constraints

Govern and design the target endpoint program

3 person-days
ES-P1-M07Planned

Approve the target platform boundary and any retained specialist tools

Govern and design the target endpoint program

3 person-daysCritical
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first.
ES-P2-M08Planned

Define migration waves and fixed sequencing criteria

Design and prove the endpoint migration

4 person-days
ES-P2-M09Planned

Define pilot success, failure, rollback, and evidence criteria

Design and prove the endpoint migration

3 person-days
ES-P2-M10Planned

Prepare the target policy, configuration, role, and exception baseline

Design and prove the endpoint migration

5 person-daysCritical
ES-P2-M11Planned

Define coexistence controls for overlapping or conflicting agents

Design and prove the endpoint migration

4 person-daysCritical
ES-P2-M12Planned

Pilot a representative endpoint group with an approved rollback path

Design and prove the endpoint migration

5 person-daysCritical
ES-P2-M13Planned

Validate control coverage, operational workflows, performance, and support readiness

Design and prove the endpoint migration

5 person-daysCritical
ES-P2-M14Planned

Resolve pilot gaps and record the production go or no-go decision

Design and prove the endpoint migration

3 person-daysCritical
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first.
ES-P3-M15Planned

Migrate production waves with bounded pause and rollback criteria

Migrate, retire, and operate endpoint controls

8 person-daysCritical
ES-P3-M16Planned

Confirm target coverage and remove legacy agents from migrated endpoints

Migrate, retire, and operate endpoint controls

5 person-daysCritical
ES-P3-M17Planned

Retire approved legacy services, data flows, access, and contracts

Migrate, retire, and operate endpoint controls

4 person-daysCritical
ES-P3-M18Planned

Transfer ownership, metrics, exceptions, and executive reporting to routine operations

Migrate, retire, and operate endpoint controls

3 person-daysCritical
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first.

Critical path

15 remaining · Name the sponsor, program owner, and consolidation decision rights · Next · October 2, 2026

Dependencies

No handoffs need review

Next handoff

Name the sponsor, program owner, and consolidation decision rights · Executive sponsor · September 7, 2026