Endpoint Security Consolidation
Kanban
Move milestones through delivery states
Drag cards between columns or use each card's Move to status control. Complete requires a date and acceptance confirmation; Blocked requires a category.
Planned
18
ES-P1-M01On track
Name the sponsor, program owner, and consolidation decision rights
2 person-daysCritical
ES-P1-M02At risk
Define the endpoint populations and operating systems in scope
4 person-daysCritical
Waiting onES-P1-M01
ES-P1-M03At risk
Establish a baseline endpoint and ownership inventory process
4 person-daysCritical
Waiting onES-P1-M02
ES-P1-M04At risk
Map the current endpoint tools, agents, owners, contracts, and data flows
5 person-daysCritical
Waiting onES-P1-M02, ES-P1-M03
ES-P1-M05At risk
Define the required management, protection, detection, response, and reporting capabilities
4 person-daysCritical
Waiting onES-P1-M02, ES-P1-M04
ES-P1-M06At risk
Record platform, remote-work, offline-device, and regulated-system constraints
3 person-days
Waiting onES-P1-M02, ES-P1-M04
ES-P1-M07At risk
Approve the target platform boundary and any retained specialist tools
3 person-daysCritical
Waiting onES-P1-M05, ES-P1-M06
ES-P2-M08At risk
Define migration waves and fixed sequencing criteria
4 person-days
Waiting onES-P1-M07
ES-P2-M09At risk
Define pilot success, failure, rollback, and evidence criteria
3 person-days
Waiting onES-P1-M07, ES-P2-M08
ES-P2-M10At risk
Prepare the target policy, configuration, role, and exception baseline
5 person-daysCritical
Waiting onES-P1-M07
ES-P2-M11At risk
Define coexistence controls for overlapping or conflicting agents
4 person-daysCritical
Waiting onES-P1-M04, ES-P1-M07, ES-P2-M10
ES-P2-M12At risk
Pilot a representative endpoint group with an approved rollback path
5 person-daysCritical
Waiting onES-P2-M09, ES-P2-M10, ES-P2-M11
ES-P2-M13At risk
Validate control coverage, operational workflows, performance, and support readiness
5 person-daysCritical
Waiting onES-P2-M12
ES-P2-M14At risk
Resolve pilot gaps and record the production go or no-go decision
3 person-daysCritical
Waiting onES-P2-M13
ES-P3-M15At risk
Migrate production waves with bounded pause and rollback criteria
8 person-daysCritical
Waiting onES-P2-M14
ES-P3-M16At risk
Confirm target coverage and remove legacy agents from migrated endpoints
5 person-daysCritical
Waiting onES-P3-M15
ES-P3-M17At risk
Retire approved legacy services, data flows, access, and contracts
4 person-daysCritical
Waiting onES-P3-M16
ES-P3-M18At risk
Transfer ownership, metrics, exceptions, and executive reporting to routine operations