Endpoint Security Consolidation

Gantt

Review schedule timing and dependencies

Current planGenerated baselineTodayCritical pathComplete
Actions
ES-P1Govern and design the target endpoint program
StatusPlanned
Govern and design the target endpoint program is part of the program template. Only projects created in this program can be deleted.
ES-P1-M01Name the sponsor, program owner, and consolidation decision rights
StatusPlanned
ES-P1-M02Define the endpoint populations and operating systems in scope
StatusPlanned
ES-P1-M03Establish a baseline endpoint and ownership inventory process
StatusPlanned
ES-P1-M04Map the current endpoint tools, agents, owners, contracts, and data flows
StatusPlanned
ES-P1-M05Define the required management, protection, detection, response, and reporting capabilities
StatusPlanned
ES-P1-M06Record platform, remote-work, offline-device, and regulated-system constraints
StatusPlanned
ES-P1-M07Approve the target platform boundary and any retained specialist tools
StatusPlanned
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first.
ES-P2Design and prove the endpoint migration
StatusPlanned
Design and prove the endpoint migration is part of the program template. Only projects created in this program can be deleted.
ES-P2-M08Define migration waves and fixed sequencing criteria
StatusPlanned
ES-P2-M09Define pilot success, failure, rollback, and evidence criteria
StatusPlanned
ES-P2-M10Prepare the target policy, configuration, role, and exception baseline
StatusPlanned
ES-P2-M11Define coexistence controls for overlapping or conflicting agents
StatusPlanned
ES-P2-M12Pilot a representative endpoint group with an approved rollback path
StatusPlanned
ES-P2-M13Validate control coverage, operational workflows, performance, and support readiness
StatusPlanned
ES-P2-M14Resolve pilot gaps and record the production go or no-go decision
StatusPlanned
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first.
ES-P3Migrate, retire, and operate endpoint controls
StatusPlanned
Migrate, retire, and operate endpoint controls is part of the program template. Only projects created in this program can be deleted.
ES-P3-M15Migrate production waves with bounded pause and rollback criteria
StatusPlanned
ES-P3-M16Confirm target coverage and remove legacy agents from migrated endpoints
StatusPlanned
ES-P3-M17Retire approved legacy services, data flows, access, and contracts
StatusPlanned
ES-P3-M18Transfer ownership, metrics, exceptions, and executive reporting to routine operations
StatusPlanned
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first.
Govern and design the target endpoint program
Forecast finish
August 20, 2027
ES-P1-M01 · Name the sponsor, program owner, and consolidation decision rights
Forecast finish
October 2, 2026
Generated baseline
October 2, 2026
ES-P1-M02 · Define the endpoint populations and operating systems in scope
Forecast finish
November 27, 2026
Generated baseline
November 27, 2026
ES-P1-M03 · Establish a baseline endpoint and ownership inventory process
Forecast finish
January 22, 2027
Generated baseline
January 22, 2027
ES-P1-M04 · Map the current endpoint tools, agents, owners, contracts, and data flows
Forecast finish
April 2, 2027
Generated baseline
April 2, 2027
ES-P1-M05 · Define the required management, protection, detection, response, and reporting capabilities
Forecast finish
May 28, 2027
Generated baseline
May 28, 2027
ES-P1-M06 · Record platform, remote-work, offline-device, and regulated-system constraints
Forecast finish
July 9, 2027
Generated baseline
July 9, 2027
ES-P1-M07 · Approve the target platform boundary and any retained specialist tools
Forecast finish
August 20, 2027
Generated baseline
August 20, 2027
Design and prove the endpoint migration
Forecast finish
September 29, 2028
ES-P2-M08 · Define migration waves and fixed sequencing criteria
Forecast finish
October 15, 2027
Generated baseline
October 15, 2027
ES-P2-M09 · Define pilot success, failure, rollback, and evidence criteria
Forecast finish
November 26, 2027
Generated baseline
November 26, 2027
ES-P2-M10 · Prepare the target policy, configuration, role, and exception baseline
Forecast finish
February 4, 2028
Generated baseline
February 4, 2028
ES-P2-M11 · Define coexistence controls for overlapping or conflicting agents
Forecast finish
March 31, 2028
Generated baseline
March 31, 2028
ES-P2-M12 · Pilot a representative endpoint group with an approved rollback path
Forecast finish
June 9, 2028
Generated baseline
June 9, 2028
ES-P2-M13 · Validate control coverage, operational workflows, performance, and support readiness
Forecast finish
August 18, 2028
Generated baseline
August 18, 2028
ES-P2-M14 · Resolve pilot gaps and record the production go or no-go decision
Forecast finish
September 29, 2028
Generated baseline
September 29, 2028
Migrate, retire, and operate endpoint controls
Forecast finish
July 6, 2029
ES-P3-M15 · Migrate production waves with bounded pause and rollback criteria
Forecast finish
January 19, 2029
Generated baseline
January 19, 2029
ES-P3-M16 · Confirm target coverage and remove legacy agents from migrated endpoints
Forecast finish
March 30, 2029
Generated baseline
March 30, 2029
ES-P3-M17 · Retire approved legacy services, data flows, access, and contracts
Forecast finish
May 25, 2029
Generated baseline
May 25, 2029
ES-P3-M18 · Transfer ownership, metrics, exceptions, and executive reporting to routine operations
Forecast finish
July 6, 2029
Generated baseline
July 6, 2029

Recommendations

Recommendations requiring attention
Actions
No active recommendations for this view.
  1. No active recommendations for this view.