ES-P1Govern and design the target endpoint program
Endpoint Security Consolidation
Gantt
Review schedule timing and dependencies
Actions
StatusPlanned
ES-P1-M01Name the sponsor, program owner, and consolidation decision rights
StatusPlannedES-P1-M02Define the endpoint populations and operating systems in scope
StatusPlannedES-P1-M03Establish a baseline endpoint and ownership inventory process
StatusPlannedES-P1-M04Map the current endpoint tools, agents, owners, contracts, and data flows
StatusPlannedES-P1-M05Define the required management, protection, detection, response, and reporting capabilities
StatusPlannedES-P1-M06Record platform, remote-work, offline-device, and regulated-system constraints
StatusPlannedES-P1-M07Approve the target platform boundary and any retained specialist tools
StatusPlannedES-P2Design and prove the endpoint migration
ES-P2-M08Define migration waves and fixed sequencing criteria
StatusPlannedES-P2-M09Define pilot success, failure, rollback, and evidence criteria
StatusPlannedES-P2-M10Prepare the target policy, configuration, role, and exception baseline
StatusPlannedES-P2-M11Define coexistence controls for overlapping or conflicting agents
StatusPlannedES-P2-M12Pilot a representative endpoint group with an approved rollback path
StatusPlannedES-P2-M13Validate control coverage, operational workflows, performance, and support readiness
StatusPlannedES-P2-M14Resolve pilot gaps and record the production go or no-go decision
StatusPlannedES-P3Migrate, retire, and operate endpoint controls
ES-P3-M15Migrate production waves with bounded pause and rollback criteria
StatusPlannedES-P3-M16Confirm target coverage and remove legacy agents from migrated endpoints
StatusPlannedES-P3-M17Retire approved legacy services, data flows, access, and contracts
StatusPlannedES-P3-M18Transfer ownership, metrics, exceptions, and executive reporting to routine operations
StatusPlannedGovern and design the target endpoint program
- Forecast finish
- August 20, 2027
ES-P1-M01 · Name the sponsor, program owner, and consolidation decision rights
- Forecast finish
- October 2, 2026
- Generated baseline
- October 2, 2026
ES-P1-M02 · Define the endpoint populations and operating systems in scope
- Forecast finish
- November 27, 2026
- Generated baseline
- November 27, 2026
ES-P1-M03 · Establish a baseline endpoint and ownership inventory process
- Forecast finish
- January 22, 2027
- Generated baseline
- January 22, 2027
ES-P1-M04 · Map the current endpoint tools, agents, owners, contracts, and data flows
- Forecast finish
- April 2, 2027
- Generated baseline
- April 2, 2027
ES-P1-M05 · Define the required management, protection, detection, response, and reporting capabilities
- Forecast finish
- May 28, 2027
- Generated baseline
- May 28, 2027
ES-P1-M06 · Record platform, remote-work, offline-device, and regulated-system constraints
- Forecast finish
- July 9, 2027
- Generated baseline
- July 9, 2027
ES-P1-M07 · Approve the target platform boundary and any retained specialist tools
- Forecast finish
- August 20, 2027
- Generated baseline
- August 20, 2027
Design and prove the endpoint migration
- Forecast finish
- September 29, 2028
ES-P2-M08 · Define migration waves and fixed sequencing criteria
- Forecast finish
- October 15, 2027
- Generated baseline
- October 15, 2027
ES-P2-M09 · Define pilot success, failure, rollback, and evidence criteria
- Forecast finish
- November 26, 2027
- Generated baseline
- November 26, 2027
ES-P2-M10 · Prepare the target policy, configuration, role, and exception baseline
- Forecast finish
- February 4, 2028
- Generated baseline
- February 4, 2028
ES-P2-M11 · Define coexistence controls for overlapping or conflicting agents
- Forecast finish
- March 31, 2028
- Generated baseline
- March 31, 2028
ES-P2-M12 · Pilot a representative endpoint group with an approved rollback path
- Forecast finish
- June 9, 2028
- Generated baseline
- June 9, 2028
ES-P2-M13 · Validate control coverage, operational workflows, performance, and support readiness
- Forecast finish
- August 18, 2028
- Generated baseline
- August 18, 2028
ES-P2-M14 · Resolve pilot gaps and record the production go or no-go decision
- Forecast finish
- September 29, 2028
- Generated baseline
- September 29, 2028
Migrate, retire, and operate endpoint controls
- Forecast finish
- July 6, 2029
ES-P3-M15 · Migrate production waves with bounded pause and rollback criteria
- Forecast finish
- January 19, 2029
- Generated baseline
- January 19, 2029
ES-P3-M16 · Confirm target coverage and remove legacy agents from migrated endpoints
- Forecast finish
- March 30, 2029
- Generated baseline
- March 30, 2029
ES-P3-M17 · Retire approved legacy services, data flows, access, and contracts
- Forecast finish
- May 25, 2029
- Generated baseline
- May 25, 2029
ES-P3-M18 · Transfer ownership, metrics, exceptions, and executive reporting to routine operations
- Forecast finish
- July 6, 2029
- Generated baseline
- July 6, 2029