Ransomware Resilience

Program overview

See what is on track, blocked, and due next.

Value of assets
Not provided Program-wide
Add value

Project schedule

Planned scheduleCompletedForecast difference
Project schedule percentage done, finish, and outlook
17%
Planned finishOct 30, 2026
Forecast finishMar 05, 2027
Schedule variance126 days late
Capacity5 days needed
17%
Planned finishFeb 19, 2027
Forecast finishMar 26, 2027
Schedule variance35 days late
Capacity8 days needed
22%
Planned finishFeb 05, 2027
Forecast finishFeb 26, 2027
Schedule variance21 days late
Capacity8 days needed
33%
Planned finishDec 18, 2026
Forecast finishDec 18, 2026
Schedule varianceNone
Capacity63.5 days available
  1. Done
    17%
    Finish
    Planned finishOct 30, 2026
    Forecast finishMar 05, 2027
    Outlook
    Schedule variance126 days late
    Capacity5 days needed
  2. Done
    17%
    Finish
    Planned finishFeb 19, 2027
    Forecast finishMar 26, 2027
    Outlook
    Schedule variance35 days late
    Capacity8 days needed
  3. Done
    22%
    Finish
    Planned finishFeb 05, 2027
    Forecast finishFeb 26, 2027
    Outlook
    Schedule variance21 days late
    Capacity8 days needed
  4. Done
    33%
    Finish
    Planned finishDec 18, 2026
    Forecast finishDec 18, 2026
    Outlook
    Schedule varianceNone
    Capacity63.5 days available

Recommendations

Recommendations requiring attention
Actions
London
RR-P02 Prepare recovery access and restorationProject
RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.
Resolve the technical dependency, then retest affected work.Feb 05, 2027
London
RR-P04 Reduce, detect, and exercise ransomware riskProject
RR-18 cannot meet its Feb 05, 2027 target while RR-14 finishes on Mar 26, 2027.
Confirm the external owner, commitment, and date.Feb 05, 2027
London
RR-P02 Prepare recovery access and restorationProject
21 person-days short of the capacity needed by 2027-02-05. Forecast finish 2027-03-26 is 49 days after the target.
Resolve “Test restoration of critical services” with Recovery lead. Close the 21 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Feb 12, 2027
  1. Site
    London
    RR-P02 Prepare recovery access and restorationProject

    Impact

    RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.

    Recommendations

    Resolve the technical dependency, then retest affected work.

    NeededFeb 05, 2027
  2. Site
    London
    RR-P04 Reduce, detect, and exercise ransomware riskProject

    Impact

    RR-18 cannot meet its Feb 05, 2027 target while RR-14 finishes on Mar 26, 2027.

    Recommendations

    Confirm the external owner, commitment, and date.

    NeededFeb 05, 2027
  3. Site
    London
    RR-P02 Prepare recovery access and restorationProject

    Impact

    21 person-days short of the capacity needed by 2027-02-05. Forecast finish 2027-03-26 is 49 days after the target.

    Recommendations

    Resolve “Test restoration of critical services” with Recovery lead. Close the 21 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.

    NeededFeb 12, 2027