Ransomware Resilience
Program overview
See what is on track, blocked, and due next.
- Value of assets
- Not provided Program-wide
- Add value
Project schedule
Planned scheduleCompletedForecast difference
RR-P01 Govern ransomware resilienceAt riskIn progress | 17% | Planned finishOct 30, 2026 Forecast finishMar 05, 2027 | Schedule variance126 days late Capacity5 days needed | |
|---|---|---|---|---|
RR-P04 Reduce, detect, and exercise ransomware riskOff trackBlocked | 17% | Planned finishFeb 19, 2027 Forecast finishMar 26, 2027 | Schedule variance35 days late Capacity8 days needed | |
RR-P02 Prepare recovery access and restorationOff trackBlocked | 22% | Planned finishFeb 05, 2027 Forecast finishFeb 26, 2027 | Schedule variance21 days late Capacity8 days needed | |
RR-P03 Design resilient service boundariesOn trackPlanned | 33% | Planned finishDec 18, 2026 Forecast finishDec 18, 2026 | Schedule varianceNone Capacity63.5 days available |
- RR-P01 Govern ransomware resilienceAt riskIn progress
- Done
- 17%
- Finish
- Planned finishOct 30, 2026Forecast finishMar 05, 2027
- Outlook
- Schedule variance126 days lateCapacity5 days needed
- RR-P04 Reduce, detect, and exercise ransomware riskOff trackBlocked
- Done
- 17%
- Finish
- Planned finishFeb 19, 2027Forecast finishMar 26, 2027
- Outlook
- Schedule variance35 days lateCapacity8 days needed
- RR-P02 Prepare recovery access and restorationOff trackBlocked
- Done
- 22%
- Finish
- Planned finishFeb 05, 2027Forecast finishFeb 26, 2027
- Outlook
- Schedule variance21 days lateCapacity8 days needed
- RR-P03 Design resilient service boundariesOn trackPlanned
- Done
- 33%
- Finish
- Planned finishDec 18, 2026Forecast finishDec 18, 2026
- Outlook
- Schedule varianceNoneCapacity63.5 days available
Recommendations
| Actions | |||||
|---|---|---|---|---|---|
| London | RR-P02 Prepare recovery access and restorationProject | RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target. | Resolve the technical dependency, then retest affected work. | Feb 05, 2027 | |
| London | RR-P04 Reduce, detect, and exercise ransomware riskProject | RR-18 cannot meet its Feb 05, 2027 target while RR-14 finishes on Mar 26, 2027. | Confirm the external owner, commitment, and date. | Feb 05, 2027 | |
| London | RR-P02 Prepare recovery access and restorationProject | 21 person-days short of the capacity needed by 2027-02-05. Forecast finish 2027-03-26 is 49 days after the target. | Resolve “Test restoration of critical services” with Recovery lead. Close the 21 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target. | Feb 12, 2027 |
- Site
- London
RR-P02 Prepare recovery access and restorationProjectImpact
RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.Recommendations
Resolve the technical dependency, then retest affected work.
- Site
- London
RR-P04 Reduce, detect, and exercise ransomware riskProjectImpact
RR-18 cannot meet its Feb 05, 2027 target while RR-14 finishes on Mar 26, 2027.Recommendations
Confirm the external owner, commitment, and date.
- Site
- London
RR-P02 Prepare recovery access and restorationProjectImpact
21 person-days short of the capacity needed by 2027-02-05. Forecast finish 2027-03-26 is 49 days after the target.Recommendations
Resolve “Test restoration of critical services” with Recovery lead. Close the 21 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.



