Ransomware Resilience

Kanban

Move milestones through delivery states

Drag cards between columns or use each card's Move to status control. Complete requires a date and acceptance confirmation; Blocked requires a category.

Planned

2
RR-P1-M15At risk

Operationalize the ransomware response playbook

3 person-days
Deletion is unavailable for RR-P1-M15 in this preview.
RR-P1-M16At risk

Confirm the executive crisis decision process

2 person-days

Waiting onRR-P1-M15

Deletion is unavailable for RR-P1-M16 in this preview.

In progress

3
RR-P4-M13At risk

Define detection and escalation procedures

3 person-days
Deletion is unavailable for RR-P4-M13 in this preview.
RR-P4-M14At risk

Test alert triage and isolation

2 person-days

Waiting onRR-P4-M13

Deletion is unavailable for RR-P4-M14 in this preview.
RR-P2-M01Off track

Validate clean-room identity recovery access

4 person-daysCritical
Deletion is unavailable for RR-P2-M01 in this preview.

Blocked

2
RR-P2-M17Off track

Test restoration of critical services

4 person-daysCritical

Blocked byTechnical prerequisite

Waiting onRR-P2-M01

Deletion is unavailable for RR-P2-M17 in this preview.
RR-P4-M18Off track

Run and review a ransomware exercise

3 person-daysCritical

Blocked byExternal dependency

Waiting onRR-P4-M14, RR-P1-M16, RR-P2-M17

Deletion is unavailable for RR-P4-M18 in this preview.

Complete

12
RR-P1-M01On track

Set program ownership and decisions

1 person-day
Deletion is unavailable for RR-P1-M01 in this preview.
RR-P1-M02On track

Define critical services and data

3 person-daysCritical
Deletion is unavailable for RR-P1-M02 in this preview.
RR-P1-M03On track

Approve recovery priorities and objectives

2 person-days
Deletion is unavailable for RR-P1-M03 in this preview.
RR-P3-M04On track

Design resilient service architecture

3 person-days
Deletion is unavailable for RR-P3-M04 in this preview.
RR-P2-M05On track

Separate daily and privileged administration

2 person-daysCritical
Deletion is unavailable for RR-P2-M05 in this preview.
RR-P2-M06On track

Require strong authentication

2 person-days
Deletion is unavailable for RR-P2-M06 in this preview.
RR-P2-M07On track

Define recovery access procedures

2 person-daysCritical
Deletion is unavailable for RR-P2-M07 in this preview.
RR-P4-M08On track

Set endpoint detection and isolation coverage

2 person-days
Deletion is unavailable for RR-P4-M08 in this preview.
RR-P4-M09On track

Prioritize vulnerability remediation

2 person-days
Deletion is unavailable for RR-P4-M09 in this preview.
RR-P4-M10On track

Restrict and monitor privileged access

2 person-days
Deletion is unavailable for RR-P4-M10 in this preview.
RR-P3-M11On track

Segment critical networks and services

3 person-days
Deletion is unavailable for RR-P3-M11 in this preview.
RR-P2-M12On track

Establish isolated backup copies

4 person-daysCritical
Deletion is unavailable for RR-P2-M12 in this preview.

Recommendations

Recommendations requiring attention
Actions
London
RR-P02 Prepare recovery access and restorationProject
RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.
Resolve the technical dependency, then retest affected work.Feb 05, 2027
London
RR-P04 Reduce, detect, and exercise ransomware riskProject
RR-18 cannot meet its Feb 05, 2027 target while RR-14 finishes on Mar 26, 2027.
Confirm the external owner, commitment, and date.Feb 05, 2027
London
RR-P02 Prepare recovery access and restorationProject
21 person-days short of the capacity needed by 2027-02-05. Forecast finish 2027-03-26 is 49 days after the target.
Resolve “Test restoration of critical services” with Recovery lead. Close the 21 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Feb 12, 2027
  1. Site
    London
    RR-P02 Prepare recovery access and restorationProject

    Impact

    RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.

    Recommendations

    Resolve the technical dependency, then retest affected work.

    NeededFeb 05, 2027
  2. Site
    London
    RR-P04 Reduce, detect, and exercise ransomware riskProject

    Impact

    RR-18 cannot meet its Feb 05, 2027 target while RR-14 finishes on Mar 26, 2027.

    Recommendations

    Confirm the external owner, commitment, and date.

    NeededFeb 05, 2027
  3. Site
    London
    RR-P02 Prepare recovery access and restorationProject

    Impact

    21 person-days short of the capacity needed by 2027-02-05. Forecast finish 2027-03-26 is 49 days after the target.

    Recommendations

    Resolve “Test restoration of critical services” with Recovery lead. Close the 21 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.

    NeededFeb 12, 2027