OT/ICS Security Improvement
Kanban
Move milestones through delivery states
Drag cards between columns or use each card's Move to status control. Complete requires a date and acceptance confirmation; Blocked requires a category.
Planned
19
OT-P1-M02At risk
Define the system under consideration
4 person-daysCritical
Waiting onOT-P1-M01
OT-P1-M03At risk
Map critical physical functions and consequences
4 person-days
Waiting onOT-P1-M02
OT-P1-M04At risk
Approve the OT risk and acceptance method
4 person-days
Waiting onOT-P1-M03
OT-P2-M01At risk
Establish the authoritative OT inventory
5 person-daysCritical
Waiting onOT-P1-M02
OT-P2-M02At risk
Partition the system into zones and conduits
5 person-daysCritical
Waiting onOT-P2-M01
OT-P2-M03At risk
Approve target security levels and requirements
5 person-daysCritical
Waiting onOT-P1-M04, OT-P2-M02
OT-P3-M01At risk
Govern OT identity and remote access
4 person-days
Waiting onOT-P1-M02
OT-P3-M02At risk
Set service-provider security profiles
4 person-days
Waiting onOT-P3-M01
OT-P3-M03At risk
Approve legacy and maintenance constraints
4 person-daysCritical
Waiting onOT-P2-M03, OT-P3-M02
OT-P4-M01At risk
Implement zone and conduit security requirements
7 person-daysCritical
Waiting onOT-P2-M03, OT-P3-M03
OT-P4-M02At risk
Control secure change and vulnerability treatment
5 person-daysCritical
Waiting onOT-P4-M01
OT-P4-M03At risk
Operate OT monitoring and detection
5 person-days
Waiting onOT-P4-M01
OT-P4-M04At risk
Prepare trusted OT restoration assets
5 person-daysCritical
Waiting onOT-P4-M02, OT-P4-M03
OT-P5-M01At risk
Prepare OT incident response
5 person-days
Waiting onOT-P3-M03, OT-P4-M03
OT-P5-M02At risk
Approve degraded operation and safe-state strategies