Approve intended and prohibited AI use Move to status Planned In progress Blocked Complete Due Aug 28, 2026 2 person-days Critical
Waiting on AG-P1-M01
Inventory AI systems and dependencies Move to status Planned In progress Blocked Complete Due Sep 11, 2026 3 person-days Critical
Waiting on AG-P1-M01, AG-P1-M02
Classify AI risk and required assurance Move to status Planned In progress Blocked Complete Due Sep 18, 2026 2 person-days Critical
Waiting on AG-P1-M02, AG-P1-M03
Create cross-functional applicability intake Move to status Planned In progress Blocked Complete Due Sep 25, 2026 2 person-days
Waiting on AG-P1-M04
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first. Govern AI data rights and provenance Move to status Planned In progress Blocked Complete Due Oct 9, 2026 3 person-days Critical
Waiting on AG-P1-M03, AG-P1-M04
Assess models, services, and suppliers Move to status Planned In progress Blocked Complete Due Oct 23, 2026 3 person-days
Waiting on AG-P1-M03, AG-P1-M04
Threat-model each material AI system Move to status Planned In progress Blocked Complete Due Nov 6, 2026 3 person-days Critical
Waiting on AG-P1-M03, AG-P1-M04, AG-P2-M06, AG-P2-M07
Constrain AI identities, tools, and agency Move to status Planned In progress Blocked Complete Due Nov 20, 2026 3 person-days Critical
Waiting on AG-P2-M08
Set security and privacy requirements Move to status Planned In progress Blocked Complete Due Nov 27, 2026 2 person-days Critical
Waiting on AG-P1-M05, AG-P2-M06, AG-P2-M08, AG-P2-M09
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first. Define evaluations and release thresholds Move to status Planned In progress Blocked Complete Due Dec 11, 2026 4 person-days Critical
Waiting on AG-P1-M04, AG-P2-M08, AG-P2-M10
Design meaningful human oversight Move to status Planned In progress Blocked Complete Due Dec 18, 2026 2 person-days
Waiting on AG-P1-M04, AG-P2-M10
Secure deployment and change control Move to status Planned In progress Blocked Complete Due Jan 1, 2027 3 person-days Critical
Waiting on AG-P2-M07, AG-P2-M09, AG-P2-M10, AG-P3-M11, AG-P3-M12
Monitor behavior, controls, and resource use Move to status Planned In progress Blocked Complete Due Jan 15, 2027 3 person-days Critical
Waiting on AG-P3-M11, AG-P4-M13
Communicate use, limits, and recourse Move to status Planned In progress Blocked Complete Due Jan 22, 2027 2 person-days
Waiting on AG-P1-M05, AG-P3-M11, AG-P3-M12
A project acceptance milestone cannot be deleted. Add or assign a replacement acceptance milestone first. Prepare AI incident, rollback, and retirement Move to status Planned In progress Blocked Complete Due Feb 5, 2027 3 person-days Critical
Waiting on AG-P4-M13, AG-P4-M14
Run a bounded pilot and adversarial assessment Move to status Planned In progress Blocked Complete Due Feb 19, 2027 4 person-days Critical
Waiting on AG-P3-M11, AG-P4-M13, AG-P4-M14, AG-P4-M16
Approve operation and recurring review Move to status Planned In progress Blocked Complete Due Feb 26, 2027 2 person-days Critical
Waiting on AG-P3-M15, AG-P4-M16, AG-P4-M17